Procurement Simulation

If this building were publicly commissioned, its budget would determine which award procedure (Vergabeverfahren) German procurement law requires. Configured building: Vehicle Shelter, €52,500 change it in the simulation.

State (Land)
Direktauftragdirect award without competition

Below €50,000 net, the contracting authority may award the contract directly to a single company, no competitive process required.

Statutory referenceVOB/A §3a Abs. 1 (as amended 01.01.2026)
Indicative duration~1 day – 1 week
Net construction value€40,588
BerlAVG (Berliner Ausschreibungs- und Vergabegesetz)additional Berlin obligations
  • Vergabemindestentgelt — bidders must declare payment of the Berlin minimum procurement wage
  • Tariftreue — declaration of compliance with the relevant collective wage agreement
  • Frauenförderung — women's-advancement declaration (Frauenförderverordnung) above certain contract values
  • VwVBU environmental criteria — mandatory environmental requirements in the specification, per the Verwaltungsvorschrift Beschaffung und Umwelt

This procedure runs before construction can start — its duration adds to, not overlaps with, the build schedule (see About).

Indicative, educational simulation — not legal advice. Thresholds as of July 2026 (Vergabebeschleunigungsgesetz, EU works threshold 2026/2027). Net construction value approximated from the gross budget above (÷1.19 VAT, 8% planning share removed); real net-value assessment follows VgV/VOB/A contract-splitting rules.

This simulation covers three simple public-building typologies — real projects are rarely that clean. For more complex buildings (schools, hospitals, mixed-use), Meile + Stein can deliver the real procurement and Lean-schedule calculation.

Want to audit a project? Ask us →